A Way to Show % Complete without having to Hoover over the Progress (progress only shows hours)?

For example I see:

But, when I hoover over I see: Items completed: 15 out of 165 (9%)

I'd like to see this 9% without hoovering.  Is there ANY way?

0 votes



One answer

Permanent link


Not sure why it didn't take the screen shot...which shows the Progress: 82/2,059 h

0 votes

Comments

And to be able to see the hours as a Percentage.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Apr 24 '17, 3:57 p.m.

Question was seen: 968 times

Last updated: Apr 24 '17, 5:26 p.m.

Confirmation Cancel Confirm