RQM: dependencies between Test Plan and Test Cases
In RQM we need to create dependencies between Test Plan and Test Cases
One Test Plan has n number of test cases.
If all Test cases are approved (State in Action) then only Test Plan has to be approved.(Action State can be changed to Approve State)
If any one of the test case is not approved then Test Plan should not get approved means (Action Sate cannot be changed to approved state)
What are the possibilities to have dependencies between test plan and test case?
Accepted answer
Hi Priya,
you can define "preconditions & Follow-up Actions" in "Manage this project area":
Please take also in account that user with different roles have different rights.
E.g. someone with role "Data Migration Administrator" can always save a test plan because this role has not preconditions.
Hope this helps, Jörg