 Hello, 

I wanted to export a template and imported in prod from dev, is there any issue doing on this way, what could happen if import it in existing Project area with existing process, it is possible?

One answer



permanent link
Donald Nong (14.5k614) | answered Mar 23 '17, 5:35 p.m.

You cannot import a template into any existing projects. So no harm will be done.