Timelines and user process role data for reporting in BIRT

 Hi,


I am using BIRT 3.2.0 with RTC 6.0.2 and SQL Server. Is there any way we can fetch user process roles and timeline start/end dates for reporting in BIRT?


0 votes

Comments

 I got the answer


inside RIDW we have these views:

RIDW.VW_TEAM_ROLE and 
RIDW.VW_TEAM_ROLE_MEMBER_LOOKUP 
RIDW.VW_ITERATION (includes start and end date)

These can be used to report in BIRT if using JDBC connection  


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 481
× 360
× 324

Question asked: Feb 13 '17, 5:23 a.m.

Question was seen: 2,091 times

Last updated: Feb 13 '17, 11:41 a.m.

Confirmation Cancel Confirm