I am not able to produce this scenario where baseline has changes over it but graph is not showing any triangle with red mark which is show below , please explain when do we get this symbol if I have understood it wrongly.

0 votes


Accepted answer

Permanent link

Sorry , got to know the solution. Here if we try to deliver changes from one stream to another then you normally observe this triangle symbol. Earlier I was delivering changes from repository workspace to Stream.

David Lafreniere selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019
× 1,202
× 84

Question asked: Jan 12 '17, 8:22 a.m.

Question was seen: 2,612 times

Last updated: Oct 11 '17, 3:22 p.m.

Confirmation Cancel Confirm