Hello,
-thanks in advance
|
Accepted answer
![]()
Geoffrey Clemm (30.1k●2●30●35)
| answered Dec 03 '13, 12:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Linking a task to a particular baseline is not currently supported, but is requested in work item support associating baselines and snapshots to work items / change requests (169444) .
Timur Markunin selected this answer as the correct answer
Comments Thanks Geoffrey!
Do you know if it's possible to track component/snapshot state (without additional tracking workitem)?
-thanks in advance
|
One other answer
![]()
You can add a snapshot url using the "Add Related Artifact" in the Links section. Not sure about baseline.
|