How to link task to a component baseline?


Timur Markunin (6495161145) | asked Dec 02 '13, 8:21 a.m.
retagged Dec 16 '13, 11:44 a.m. by David Lafreniere (4.6k7)
Hello,

 Is it possible to link task and particular component baseline/stream snapshot  (not changeset)?

-thanks in advance

Accepted answer


permanent link
Geoffrey Clemm (29.9k23035) | answered Dec 03 '13, 12:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Linking a task to a particular baseline is not currently supported, but is requested in work item support associating baselines and snapshots to work items / change requests (169444) .
Timur Markunin selected this answer as the correct answer

Comments
Timur Markunin commented Dec 03 '13, 1:15 a.m.

 Thanks Geoffrey!


Do you know if it's possible to track component/snapshot state (without additional tracking workitem)?

-thanks in advance

One other answer



permanent link
Shashikant Padur (4.2k27) | answered Dec 02 '13, 10:30 p.m.
JAZZ DEVELOPER
 You can add a snapshot url using the "Add Related Artifact" in the Links section. Not sure about baseline.