Who has upgraded to DNG 6.0.2 and what was your experience?
Working with a client that has a large DNG project area (250k artifacts, 1k module baselines). The upgrade from 5.0.2 to 6.0.2 took 6 days to complete. The majority of that time (95%) was converting the module baselines to project baselines. Now we are working with IBM to fix performance issues and multiple features that are not working.
Who else has upgraded to DNG 6.0.2? What was the largest project area (# of artifacts)? How many module baselines? What was your experience with the upgrade?
Thanks!