Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Who has upgraded to DNG 6.0.2 and what was your experience?

 Working with a client that has a large DNG project area (250k artifacts, 1k module baselines).  The upgrade from 5.0.2 to 6.0.2 took 6 days to complete.  The majority of that time (95%) was converting the module baselines to project baselines.  Now we are working with IBM to fix performance issues and multiple features that are not working.

Who else has upgraded to DNG 6.0.2?  What was the largest project area (# of artifacts)?  How many module baselines?  What was your experience with the upgrade?

Thanks!

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 12 '16, 5:33 p.m.

Question was seen: 1,631 times

Last updated: Dec 12 '16, 5:33 p.m.

Confirmation Cancel Confirm