Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Managing Product level progress

 Hello ,

We have two RTC projects, 
The projects are managed By WI (Epic's) using SCRUM template (RTC V5).
We want to display the big picture for the WI (from two Project's). So, the development of the "Epic" is done using those two RTC projects. 

To do this , we created another project for management. 
Within this project we created a WI (Epic) and connected it to the Epics (from two project's). 

And the problem is: We can not see anything new at the progress bar ...

Any idea why?

Thanks. 


0 votes



One answer

Permanent link
You can create a cross-project plan, but you cannot (as of 6.0.3) roll up progress across multiple project areas.

0 votes

Comments

 Hi Geoff,

If Roy will use some SAFe templates and project that manage other project Artifacts,  we he be able to achieve it? 

This is how cross project planning works: https://jazz.net/library/article/1152

SAFe also depends on this feature to track across project areas.

SAFe just uses cross-project planning views ... it doesn't introduce new underlying functionality, so you can get a roll-up schedule (which is available for all cross-project plans), but you cannot get a roll-up of progress (e.g. a progress bar).

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 18 '16, 9:04 a.m.

Question was seen: 2,014 times

Last updated: Sep 19 '16, 9:22 a.m.

Confirmation Cancel Confirm