What are the Kanban setup options in version 4.0.6?
![]()
Rational Team Concert 4.0.6
I would like to know what are the options for configuring Kanban in version 4.0.6? Template, configuration, etc. 1. Kanban template 2. Prioritize by priority and date submitted 3. Merge work items 4. Can you have swimlanes for priority on the Kanban board in RTC? |
Accepted answer
![]()
Ralph Schoon (62.0k●3●36●43)
| answered Aug 02 '16, 3:36 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
1. Kanban is just a special display option in a plan view. The view is available for all project templates as far as I can tell. So you can basically create a new view in a plan, display it as Kanban.
2. There is no special functionality for this 3. Makes no sense 4. "Swimlanes" are for state only Daniel Ruebush selected this answer as the correct answer
|