Why is the PI Objective in the SAFe template not a Plan Item like Feature, Program Epic and Story?


Guido Schneider (3.4k1486115) | asked Jul 25 '16, 6:11 a.m.

Hello,

I have a short question:

Why is the PI Objective in the SAFe Program and Team template 3.0 not a Plan Item like Feature, Program Epic and Story? (Also in the 4.0 Update document it's not mentioned to change.=

Having it as execution item will give issues on plans, when the include all items checker is not selected, to exclude all execution items on plan load.

Regards
Guido Schneider


Accepted answer


permanent link
Amy Silberbauer (30657) | answered Jul 27 '16, 4:19 p.m.
JAZZ DEVELOPER
Hi,
No real reason for it. I can change it in the SAFe 4.0 template under development (and you can certainly change it yourself in the delivered templates).
Amy
Guido Schneider selected this answer as the correct answer

Comments
Guido Schneider commented Jul 28 '16, 3:44 a.m.

Thanks Amy,

I think it makes sense to change this in the product for 4.0 and have this also in your documents for manual adaption of the process.

regards

Guido