Why is the PI Objective in the SAFe template not a Plan Item like Feature, Program Epic and Story?

Hello,

I have a short question:

Why is the PI Objective in the SAFe Program and Team template 3.0 not a Plan Item like Feature, Program Epic and Story? (Also in the 4.0 Update document it's not mentioned to change.=

Having it as execution item will give issues on plans, when the include all items checker is not selected, to exclude all execution items on plan load.

Regards
Guido Schneider


0 votes


Accepted answer

Permanent link
Hi,
No real reason for it. I can change it in the SAFe 4.0 template under development (and you can certainly change it yourself in the delivered templates).
Amy
Guido Schneider selected this answer as the correct answer

0 votes

Comments

Thanks Amy,

I think it makes sense to change this in the product for 4.0 and have this also in your documents for manual adaption of the process.

regards

Guido

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221
× 21

Question asked: Jul 25 '16, 6:11 a.m.

Question was seen: 2,307 times

Last updated: Jul 28 '16, 3:44 a.m.

Confirmation Cancel Confirm