Report Builder: Pick Test Plan as a relationship for a Test Case Result is not possible


Markus Farnung (141218) | asked Jul 21 '16, 4:52 a.m.
In the Report Builder I selected the Test Case Result as an artifact to start with.
In the Traceability links I want to pick a Test Plan as a relationship. But this is not possible (with a Work Item it is possible !?!?!?!).
If I look at a Test Case Result example in RQM I can see the related Test Plan.
So why can I not select it in the Report Builder?

Accepted answer


permanent link
Francesco Chiossi (5.7k11119) | answered Jul 22 '16, 5:36 a.m.
edited Jul 22 '16, 5:39 a.m.
Hello Markus,

if you want to get the test plan associated to a test case result you need to use 2 traceability links:
Test Case Result > Test Case Execution Record > Test Plan



Best Regards,
Francesco Chiossi
Markus Farnung selected this answer as the correct answer