Hi
Looking at using approvals in RTC 2.0 for an upcoming project. We have a requirement that once a work item is approved if it then changes ( probably only the description field ) then we need to have it re-approved. I have seen a few people in the forums ask similar questions but I didn't find the answer. Is this possible in 2.0 and if so, how? Many thanks David |
One answer
Looking at using approvals in RTC 2.0 for an upcoming project. There is currently no out-of-the-box follow-up action that would enforce this constraint. It shouldn't be hard to write such a custom follow-up action, however. You could also create an enhancement request so we can consider this for a future release. -- Regards, Patrick Jazz Work Item Team |
Your answer