RTC usage by the management
Hello
I am posting this question on behalf of a customer.
We've been using RTC for 3+ years and have just recently upgraded to v6.
We have a number of projects, using scrum. Each project has 1-2 teams allocated with 1-2 timeline(s).
We use sprint plans, release plans and product backlog plans for planning.
We use Eclipse & Web. The below questions apply to v6.
How can we get an overview of our entire resource pool ?
We need high level data of how the various individuals & the teams are allocated and how much of a load they are introduced to so that we can
manage resources optimally.
How can we get an overview of our projects' progress/status ?
Each project has their own dashboard. Is it possbile to get a dashboard on all projects in RTC to see KPIs ?
How can a single resource see all his/her work across projects (under 'My work' the resource can only see work per project) ?
Thank you in advance.
I am posting this question on behalf of a customer.
We've been using RTC for 3+ years and have just recently upgraded to v6.
We have a number of projects, using scrum. Each project has 1-2 teams allocated with 1-2 timeline(s).
We use sprint plans, release plans and product backlog plans for planning.
We use Eclipse & Web. The below questions apply to v6.
How can we get an overview of our entire resource pool ?
We need high level data of how the various individuals & the teams are allocated and how much of a load they are introduced to so that we can
manage resources optimally.
How can we get an overview of our projects' progress/status ?
Each project has their own dashboard. Is it possbile to get a dashboard on all projects in RTC to see KPIs ?
How can a single resource see all his/her work across projects (under 'My work' the resource can only see work per project) ?
Thank you in advance.