We associate a Change set to a Task
I want to know if it is possible to allow the task to be "Verified" only if the change set has been delivered? Many cases that a change set is associated but not delivered but task is closed |
One answer
I do not know of a way to do this programmatically.
The verifier can use "Locate Change Sets" to verify that the change sets attached to the work item are in the expected stream. Ruby Comments
Karthik Krishnan
commented Aug 13 '15, 11:23 a.m.
Thanks. I was more looking to as a precondition :)
|