It's all about the answers!

Ask a question

planning - overview in same format


Bernd van Oostrum (21724768) | asked Aug 03 '15, 5:07 a.m.
Estimates for workitems can be entered in weeks, days, hours, ...
Is there a way to display these estimates in the plan all in the same way? (everything in days even if entered in hours)

Regards,
Bernd.

Accepted answer


permanent link
Ralph Schoon (62.3k33643) | answered Aug 03 '15, 5:52 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You can enforce to show estimates in hours.




Bernd van Oostrum selected this answer as the correct answer

Your answer


Register or to post your answer.