Hi, is there a way to restrict who can create Component Baselines?

After some investigation, I think in 2.0, if you have permission to
deliver code to a specific component, then you have also permission to
create and deliver a baseline.

In my scenario, we would like to have a deeper granularity to inspect
the type of deliver and be able to restrict baseline creation and
deliver to a specific role.

Is this possible? Any pointer would be appreciated...

Thanks,

Chemi.

0 votes



One answer

Permanent link
I think you can do this by process configuration.
1. Open project area editor
2. Go to Process Configuration tab
3. Open "Team Configuration"->"Permissions"
4. Select "Show all actions and roles" in right side panel
5. See "Source Control"->"Save Baseline (server)"

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jul 11 '09, 4:18 a.m.

Question was seen: 3,694 times

Last updated: Jul 11 '09, 4:18 a.m.

Confirmation Cancel Confirm