Create a baseline for a collection in RDNG
Hi,
I found a way to create a baseline for the whole PA in RDNG, however I'm currently would like to create a baseline for a specific collection and follow that only. Is it possible to restrict the baseline for one collection only? The create baseline button does not give me such option and I have read all the IBM knowledge's without any luck on the matter. I'm currently using the 5.0.2 version of RDNG.
Thanks for your help in advance!
|
One answer
In RDNG 5.0.2 you won't be able to baseline just a collection.
You can baseline the whole project giving it a name meaningful of what's significant in that baseline.
Also, if you have baselines 1 and 2, for instance, you can compare what the collections contents were in each of the baselines (there's a Compare Collections control inside the Collection for that).
Alternatively, you can have those requirements organized in a Module and baseline the Module (there's a Baseline Module section inside the Module for that).
|