RTC Clearcase Synchronization fails after moving the Synchronization to another project area.
Dear Experts,
We are working on importing Clearcase source code into RTC. In RTC we have all the component of the Project Area A is owned by Project Area B. So we trying as a experiment how it will works on different scenarios.
We created the Sync Stream in Project Area B and imported a stream to the Project Area B. Later we change the owner of the Stream to Project Area A and Sync workitem for checkins was moved to Project Area A as well,
whereas components are still owned by Project Area B.
Now the Synchronization fails with error message " the template workitem must reside in the same project area as the synchronization stream" though in this case both are same.
After that we just moved the workitem to Project Area B itself and ran the Sync and it got succeeded.
I am bit confused here, how the CC tools works. As mentioned the error the Synchronization Stream's project area and workitems project both are not same and it works, but the vice versa doesnot work.
Is this ownership is actually for stream or components?
Thanks
Anbu
Comments
Geoffrey Clemm
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Jun 21 '15, 1:32 a.m.Could you post a copy of the stack trace? (You might have to post it as an answer, and then modify that answer to be a comment).
Anbarasu Arivoli
Jun 22 '15, 6:22 a.m.Hi Geoff,