RTC Customization Attribute - Script


Cláudio de Sá Rodrigues (28819) | asked Apr 22 '15, 9:31 a.m.
Does anyone know if it's possible to get the value of the cumulative time in "Non-Attribute-based Presentation - Work Progress" shown in the presentation of a work item? I wanted to take the value and automatically place them on the attribute estimated time father work item.  I'm using version 4.0.5.

Thank you.

One answer



permanent link
Robert Carter (42928789) | answered Apr 22 '15, 10:38 a.m.
I don't believe this is possible with the JavaScript Attribute customizations.  You might be able to get this information from a ProcessAdvisor or a Java Based Attribute Customization.  See this article, Java Based Attribute Customizations by Ralph.

Comments
Cláudio de Sá Rodrigues commented May 06 '15, 12:47 p.m.

Thank you Robert

Your answer


Register or to post your answer.