In RTC Defect work item will the system calculates the Time Remaining field?
Hi,
In RTC Defect work item will the system calculates the Time Remaining field? If yes, please let me know the changes that I need to make to get that done.
Thanks, anitha |
One answer
Hi Anitha,
There´s a pretty good explanation about how Time Remaining works in Scrum template in this forum topic.
https://jazz.net/forum/questions/97861/auto-calculate-the-time-remaining-field |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Hi Anitha,
Not sure which field of "Defect Workitem" you are talking about.
If "Time Remaining" field is custom attribute ??
Could you please share screen shot of "Defect Workitem" ??
Many Thanks