Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Missing Iterations when customising burndown/burnup charts

 Hi Guys,

I have multiple iterations in my project. 
When I go to the project dashboard and try to customise either a burndown or burnup report, I can only select from a subset of my iterations. 
The list of iterations is missing about half even though the number of total iterations that i can select from (below the list) is accurate. 

Has anybody encountered anything like this before? I am running RTC 4.0.6.

0 votes


Accepted answer

Permanent link
Usually this is due to
  • Not having team areas that work against the iterations
  • Not having work items planned for the iterations and the team areas
A lot of the charts require team areas - this is typically visible as team area is a parameter in that case.
Daniel Grant selected this answer as the correct answer

1 vote

Comments

 Thank for the answer Ralph,


In my case it is iterations without any assigned work items not showing.
I had assumed even empty iterations would be listed and would just load as an empty burndown/burnup chart.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Jan 22 '15, 5:55 a.m.

Question was seen: 3,162 times

Last updated: Jan 22 '15, 7:49 a.m.

Confirmation Cancel Confirm