It's all about the answers!

Ask a question

Copy step from one script to another.


Michal Steinberger (181828) | asked Jan 06 '15, 2:58 a.m.

Hi,

I'm trying to copy step from one script to another in RQM 4.0.6.

if the script is the same script i can copy but if it is a differefnt script the paste is unable and the clipboard is empty.

Michal

One answer



permanent link
Ara Masrof (3.2k15) | answered Jan 06 '15, 3:57 p.m.
JAZZ DEVELOPER
Are you selecting the Copy and Paste (Before Step, After Step and Replace Step) from the Action Menu of the specific step?
Paste into a new test Script

I was able to copy specific steps between scripts in 4.0.6 with no issues; if you following theses steps and still unable to copy successfully, please open a PMR with the Technical Support 



Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.