Will users be able to import their vacation schedule in a table format or some other format into the Scheduled Absences table in RTC? We use a Lotus Notes db to track the vacation schedules and it would be nice to export/import into RTC. Otherwise users will have to input into 2 different locations and I can foresee discrepancies between the two.
One answer
miwalker wrote:
No this is not supported. Please file an enhancement request against
Agile Planning.
--
Cheers, Johannes
Agile Planning Team