Barbara Oxenford (615) | asked Dec 09 '14, 10:15 a.m.
Having a Plan linked to a Requirement Collection, I want to generate the requirements in the collection based on the wi in the plan.  (I know how to do the opposite direction.)

One answer



permanent link
Robin Bater (3.4k47) | answered Dec 19 '14, 12:03 p.m.
JAZZ DEVELOPER
Sorry I am not aware of anything that does this automatically.

The only thing I know is from a development plan, using the traceability view,  is for each work item to add a link to a requirement and to specify create a requirement rather than link to an existing requirement. All very repetitive.

I would suggest raising an enhancement request.