How Do I configure the Estimate and time Spent fields


O. Frank Allen (16113) | asked May 06 '09, 10:15 a.m.
I would like to conifgure the Time Spent, Estimate and Correction fields to in hours not duration. for example:
"1 w 1 h" - would be configured to be "36" and "1 h 30 m" would be 90 minutes - just have the estimate in hours or minutes as entered.
Can this be configured? If not how do I achieve this functionality?
Thanks in advanced... O.Frank

2 answers



permanent link
Anuerin Diaz (4112517) | answered May 07 '09, 4:45 a.m.
this seems related to enhancement 60807.

permanent link
Johannes Rieken (1.2k1) | answered May 11 '09, 3:06 a.m.
allenof wrote:
I would like to conifgure the Time Spent, Estimate and Correction
fields to in hours not duration. for example:
"1 w 1 h" - would be configured to be "36" and
"1 h 30 m" would be 90 minutes - just have the estimate in
hours or minutes as entered.
Can this be configured? If not how do I achieve this functionality?
Thanks in advanced... O.Frank


Currently, the duration input fields are not configurable. Pls file an
enhancement request for this.

--
Cheers, Johannes
Agile Planning Team

Your answer