How do I migrate Test Manager with links to Quality Manager?
Hi,
I am busy with a client that requires the following migration:
* Rational Requisite Pro 2003 6.15.734.000 -> RRC 4.0.6
* Rational Test Manager 2003 6.15.743.00 -> RQM 4.0.6
I have already done the following (Migration Data Only):
* Upgraded Test Manager to 7.0.2
* Upgraded Requisite Pro to 7.1.4 and Installed web components. The requirements are accessible from requisiteweb. (RequisitePro and Test Manager are run from separate machines as they are not compatible on the same machine)
* Installed Jazz (JTS,RRC,RTC,RQM) 4.0.6 on a separate server (Windows Server 2008 R2 64-bit, Websphere Application Server, SQL Server 2008 R2)
* Created a link to the requisite web in the RQM application as well as the requisite pro area.
* Connected the RQM project area to the connected requisiteweb area.
* Ran the RTMMigration_3.0.0.v201311292330 wizard with connection to requisite web.
The test artifacts display properly (with some minor issues) and the logs indicate that the requirements are migrated. However, when looking at test cases and test plans none of the links to requisiteweb exist. Am I missing something? I followed all of the guides to the T.
Kind Regards
JJ Baird
Accepted answer
JJ
After the Migration completed, where are you looking to validate the Reqpro links?
You will need to add the "Requirements" section from the 'Available' to the 'Selected' sections under the Manage Sections of the Test Plan (As seen below)
If you've already done this, then I would open a PMR with the support team (please include the TM to RQM migration log)
After the Migration completed, where are you looking to validate the Reqpro links?
You will need to add the "Requirements" section from the 'Available' to the 'Selected' sections under the Manage Sections of the Test Plan (As seen below)