Hello,

I just wonder if there is any use case to have multiple RQM timelines if we have multiple projects within one Project Area and one test team responsible for all projects.

My understanding is that only one timeline can be active and so it is not possible to assign different timelines to different projects (test plan).

The work-a-round is now to have one timeline and the first level iteration is the project name and below the first iteration we can define the project dependent iterations.
The feature "current iteration" makes in this configuration no sense, hence a dummy iteration with no related release is set to current.

 Makes this set-up sense or do I miss something?

Accepted answer


permanent link
Pedro Arnoldo Machado Duran (21) | answered Jan 31 '14, 1:32 p.m.
JAZZ DEVELOPER
I let you an article related to Timelines and Iterations in Rational Quality Manager :
https://jazz.net/library/article/810
Jörg Werner selected this answer as the correct answer