can a Stakeholder change his own work environment
![]()
I am a Stakeholder in a project, can I change my "work days"?
|
Accepted answer
![]()
Lauren Hayward Schaefer (3.3k●1●14●27)
| answered Jan 02 '14, 8:45 a.m.
JAZZ DEVELOPER edited Jan 02 '14, 8:46 a.m.
Hi Shmulik,
Open your project in the web client. In the upper right corner, click on your name and select "View My Profile and Licenses." You should be able to update your schedule on the Work Environment tab. Shmulik Tamari selected this answer as the correct answer
|