Hi,

When adding a user to a team, RTC has a default set of work items that get created. I have changed a couple of the fields in tasks to be required, and this now throws the process that creates the default work items when the users are added, meaning they don't get the invite email. I could workaround this by removing the create work items follow-up action from the 'Generate Team Invitation' operation in order to still push out the email, but a couple of these work items have useful info in them.

Question:
    How can I add the task properties to the follow-up action so that the required properties get filled out?


Thanks,
Kieron

One answer



permanent link
Jared Burns (4.5k29) | answered Mar 03 '09, 10:31 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
On Tue, 03 Mar 2009 14:38:31 +0000, breark wrote:

Hi,

When adding a user to a team, RTC has a default set of work items that
get created. I have changed a couple of the fields in tasks to be
required, and this now throws the process that creates the default work
items when the users are added, meaning they don't get the invite email.
I could workaround this by removing the create work items follow-up
action from the 'Generate Team Invitation' operation in order to still
push out the email, but a couple of these work items have useful info in
them.

Question:
How can I add the task properties to the follow-up action so that the
required properties get filled out?

Thanks,
Kieron

At this time, the only fields you can configure for the invitation
workitems are the workitem type, category, summary, and description.

If there are other fields that you'd like to see supported, you'll have
to file an enhancement request.

--
Jared Burns
Jazz Process Team

Comments
Kieron Brear commented Mar 04 '09, 4:30 a.m. | edited Sep 29 '13, 4:22 p.m.

At this time, the only fields you can configure for the invitation
workitems are the workitem type, category, summary, and description.

If there are other fields that you'd like to see supported, you'll have
to file an enhancement request.

--
Jared Burns
Jazz Process Team



Thanks for the reply. I'll raise the enhancement request.

Kieron


Erik anderson commented Apr 23 '10, 7:59 a.m. | edited Sep 29 '13, 4:23 p.m.

At this time, the only fields you can configure for the invitation
workitems are the workitem type, category, summary, and description.

If there are other fields that you'd like to see supported, you'll have
to file an enhancement request.

--
Jared Burns
Jazz Process Team



Is this still true in 2.0.0.2? Is there any work planned for 3.0 that will allow us to require other properties (eg. "Found in") on Work Item save and still use "Create Initial Work Items" followup on "Generate Team Invite"?


David Zeleznik commented Jul 23 '12, 9:10 p.m. | edited Sep 29 '13, 4:23 p.m.

Is this still true for 3.0 or 4.0? If so, can you point to the enhancement request so I can vote for it?

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.