Predecessor in other RTC Project AREA
Accepted answer
Carson, the predecessor/successor is only evaluated in a plan. It is also only considering work items that are in the scope of a plan. This Scope is the owner (and its children) and the iteration (and nested iterations) selected in the plan configuration.
Workitems outside of this scope (outplaced items) might be shown under certain circumstances (if they are a parent of an item in the plan) but are completely ignored by the scheduler. So the links are not considered across projects today.
There is limited support to see schedule across project boundaries, using cross project plans.
Reference:
https://jazz.net/library/article/589
Workitems outside of this scope (outplaced items) might be shown under certain circumstances (if they are a parent of an item in the plan) but are completely ignored by the scheduler. So the links are not considered across projects today.
There is limited support to see schedule across project boundaries, using cross project plans.
Reference:
https://jazz.net/library/article/657
https://jazz.net/library/article/1152https://jazz.net/library/article/589