It's all about the answers!

Ask a question

How to integrate RQM and RTC in Project Time Line part?


bin yang (823) | asked Oct 03 '13, 4:39 a.m.

We are using both RQM and RTC for the same project.

Currently, RQM TestCases can be linked to corresponding RTC work item. But the iteration in TCER follows  RQM Project Time Line, which means the administrtor has to setup the same Project Time Line as it in RTC so that members can use this information to track the ER's history in different iterations. This actually creates a lot work load and increase the possibility of out-of-sync.

Any one knows how to integrate this part?

Any instruction?

Thanks in advance!

Sylvia

Accepted answer


permanent link
Geoffrey Clemm (30.1k33035) | answered Oct 03 '13, 11:40 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
This is not currently possible, but I agree that it should be.
This is requested in work item Share a timeline between all CLM products (217048)
Please feel free to add a comment to that work item to indicate your interest/support
bin yang selected this answer as the correct answer

One other answer



permanent link
Paul Slauenwhite (8.4k12) | answered Oct 03 '13, 8:32 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
Unfortunately, you cannot share timelines between CLM applications (RQM/RTC).

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.