RTC work environment, how to specify half day -
2 answers
Hi Tom,
You can adjust the work days at the project area level. https://jazz.net/forum/questions/90429/how-do-you-use-project-specified-work-environment-in-scrum-template explains how to do so. Unfortunately, it looks like you can only set the same number of hours per day--I don't see a way to set a half day on the 6th day. You could submit an enhancement request for this. One option might be to spread the hours out evenly across all 6 days.
You can adjust the work days at the project area level. https://jazz.net/forum/questions/90429/how-do-you-use-project-specified-work-environment-in-scrum-template explains how to do so. Unfortunately, it looks like you can only set the same number of hours per day--I don't see a way to set a half day on the 6th day. You could submit an enhancement request for this. One option might be to spread the hours out evenly across all 6 days.