RTC work environment, how to specify half day -
Our customer works 5 and 1/2 days . Is it possible to set 5 & half day work schedule at project area or at team area level instead of asking each and every users to set 4 hours for 6th day
thank you
|
2 answers
Hi Tom,
You can adjust the work days at the project area level. https://jazz.net/forum/questions/90429/how-do-you-use-project-specified-work-environment-in-scrum-template explains how to do so. Unfortunately, it looks like you can only set the same number of hours per day--I don't see a way to set a half day on the 6th day. You could submit an enhancement request for this. One option might be to spread the hours out evenly across all 6 days. |
Hi Tom,
You have to edit the work days for every user. In the web-client you have to open each user, go to work environment and add 4hours for the 6th day of work |