RTC work environment, how to specify half day -


Thomman TJ (9521111) | asked Sep 22 '13, 1:18 p.m.

Our customer works 5 and 1/2 days . Is it possible to set 5 & half day work schedule at project area or at team area level instead of asking each and every users to set 4 hours for 6th day

thank you

2 answers



permanent link
alex ioan (33710) | answered Sep 26 '13, 4:36 a.m.
Hi Tom,

You have to edit the work days for every user. In the web-client you have to open each user, go to work environment and add 4hours for the 6th day of work

permanent link
Lauren Hayward Schaefer (3.3k11727) | answered Sep 23 '13, 7:14 a.m.
JAZZ DEVELOPER
Hi Tom,

You can adjust the work days at the project area level.  https://jazz.net/forum/questions/90429/how-do-you-use-project-specified-work-environment-in-scrum-template explains how to do so.  Unfortunately, it looks like you can only set the same number of hours per day--I don't see a way to set a half day on the 6th day.  You could submit an enhancement request for this.  One option might be to spread the hours out evenly across all 6 days.