Eclipse UI - Agile planning - Progress bar
I'm using RTC v2.0 M2D1
1. Is there any way to replace the open/close based bars with estimate bars? 2. Is there any way to add a field to TASKS that allows directly input of the value of percentage complete? Thanks. |
One answer
i900621 wrote:
I'm using RTC v2.0 M2D1 Where is that? In the plan editor? 2. Is there any way to add a field to TASKS that allows directly I assume you are talking about top-level work item types like stories in the plan editor. The value of percentage completed depends on the children. Hence, updating that value is only possible by resolving child work items. -- Cheers, Johannes Agile Planning Team |