How to see how many hours team members are assigned?
Hi there,
I have searched high and low on the forums, and have yet to find any answer to my question. For a given iteration we would like to see the amount of time each team member has been assigned based on their tasks. There are charts that show the number of Stories/Tasks etc per Team Member, but none that show the number of hours assigned to a person. Any suggestions/tips? Thanks in advance Rich |
3 answers
cumbers wrote:
Hi there, Did you try the Team Load section? It lives in the Team Central view and, configured for a team and iteration, shows the available work hours per team member (based on their work time, team assignment, and absences) and how many hours are booked. For more details, see https://jazz.net/learn/content/docs/iteration-planning/#teamLoad. -- Cheers, Johannes Agile Planning Team |
That is just what I needed!
Thank you very much! |
Hello Johannes How do i get the available hours per team member in a report ? Thanks..Johnson |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.