Progress and Load Bars
Is there a way to get a list of work items that contribute to the current progress or work load bar? For example the current progress bar says X / Y hours. Is there a way to get a list of work items that sum up to X.
Sometimes it is a complete mystery to me how the numbers get there into the progress and work load bars.
Thanks
Sometimes it is a complete mystery to me how the numbers get there into the progress and work load bars.
Thanks
One answer
On Wed, 14 Jan 2009 22:27:55 +0100, lapkow
<lapkow> wrote:
Check out
https://jazz.net/learn/LearnItem.jsp?href=content/docs/iteration-planning-bars/index.html
for information about load and progress and about their computation. We
are aware of several issues with the current implementation. The progress
computation will be reworked as part of
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/66902
--
Cheers, Johannes
Agile Planning Team
<lapkow> wrote:
Is there a way to get a list of work items that contribute to the
current progress or work load bar? For example the current progress
bar says X / Y hours. Is there a way to get a list of work items that
sum up to X.
Sometimes it is a complete mystery to me how the numbers get there
into the progress and work load bars.
Check out
https://jazz.net/learn/LearnItem.jsp?href=content/docs/iteration-planning-bars/index.html
for information about load and progress and about their computation. We
are aware of several issues with the current implementation. The progress
computation will be reworked as part of
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/66902
--
Cheers, Johannes
Agile Planning Team