Summarize Time Spent


Danny Lopes (3622) | asked Jul 10 '13, 1:27 p.m.
edited Jul 12 '13, 6:35 p.m. by Millard Ellingsworth (2.5k12431)
Have you guys find a way to summarize time spent of a set of work items? I have a query in RTC that lists completed work items, but how do I know how many hours does them represent?

Regards

Danny Lopes



Comments
Millard Ellingsworth commented Jul 12 '13, 6:35 p.m.
FORUM ADMINISTRATOR / JAZZ DEVELOPER

Did you look at any of the Reports? This is the sort of functionality you are more likely to find there. 


Clement Liu commented Jul 12 '13, 7:02 p.m.

You meant something like hours roll up?


Danny Lopes commented Jul 14 '13, 1:06 p.m.

Millard, I use RTC release 3.0.1.2, and I don't think there's this Reports feature. Can you describe it or link some related article?


Clement Liu, I mean a query that could compute the total hours spent in the resultset work items filtered. Got it?


Accepted answer


permanent link
Clement Liu (1.5k54349) | answered Jul 14 '13, 1:31 p.m.
@dannyslopes, sorry, work item query wouldn't give you the sum of hours. Have your tried using RTC Plan? The progress bar would probably give what you want


Or here is the work progress report that you might be interested in:

Hope it helps. Thanks.
Danny Lopes selected this answer as the correct answer