It's all about the answers!

Ask a question

Good practices for setting up RTC environment


Paul Sims (31513421) | asked Dec 10 '08, 7:50 a.m.
I'm consulting the community because I'm not sure we're implementing good practices in setting up our RTC environment. We're using the Scrum Process Template. So far we're only using RTC for planning and tracking, so we can put SCM and build considerations aside. (Or can we?) Our organization consists of about 200 developers, testers, writers, and UX professionals organized into about 20 Scrum teams that span three geographic locations.

When we started using RTC, we created one project area, one team area, and multiple sub-team areas, one for each Scrum team. We also created one work item category per team area and associated each category with its corresponding team. So far so good? We were able to create a product backlog and sprint backlogs for each team and all seemed to work well.

We now want to track development on three different deliverables (releases). The teams and people are the same, but the releases are on slightly different schedules and are happening in parallel. Initially I thought we would use separate project areas for each release, but realized that meant duplicating team areas and reports; not what we wanted.

Earlier this week I created two additional development lines. Now we have one line for the main release, another for a feature pack, and a third for another deliverable. I created an iteration for each of the deliverables, and iterations for the sprints in each deliverable. How am I doing so far?

At that point I thought we were set but quickly learned that to have separate sprint backlogs for each development line, you also need to define separate team areas. When you create a sprint backlog, you have to specify the project area, team area, and iteration. What I found is that by selecting the team area, I am implicitly selecting the development line (release) and therefore the corresponding sprints. I was hoping that the iteration would be independent of the team area, but it is not.

Now I'm creating additional team areas for teams who are simultaneously working on two development lines. Is this the best approach? Can we still share the teams' work item categories across the three development lines, or should I be thinking about creating additional work item categories too?

I was hoping to keep the structure simple, but it's grown more complicated now that we have three development lines. Is there a better way to set up our environment?

Paul Sims
IBM WebSphere Commerce

32 answers



permanent link
Mauricio Silclir (9184) | answered Jul 21 '10, 1:23 p.m.
Walter,
I definitely think this is a wonderful idea. As we started our RTC configuration from scratch, this information would enable us to analyze possible gaps, best practices, and if applicable I could also share my own experiences, based on your examples.

Thanks!

Hi all,

Thanks to those who have posted on this topic already.

Nick, I took a look at the article in your earlier reply. I didn't even know that it existed, but in reading it, I realized that we were following most of the recommendations in it. That may be because of the fact that IBM helped set up our environment here.

I would like to add my "uninvited" opinion on this topic. In reading the article, it is apparent that it really is all in the "planning". That is, creating plans, teams, projects, etc..., in RTC is relatively easy. The hard part of it is all in the "up front" planning (and getting everyone involved to agree to the plan). Once you get though that part, the implementation is easy. I think most of the posters to this discussion would agree with that.

Having said that, I would like to volunteer to help with taking this subject further. I am not an "expert" in this subject matter (others in this discussion may be along with the authors of the article), but I can provide some examples of how we work with this topic here.

Thanks,

- Walter

Me too.

I find "structuring development lines" is quite confusing during a pilot.

BTW, I can find little guidance on this subject in Internet.

Hello All,

I am wondering if there is any artifact out of the earlier discussions. I'm also very interested in such an article.

permanent link
Douglas Shaw (6) | answered Sep 23 '10, 12:46 p.m.
I have created an RTC project with three sprints/iterations in one project. When viewing the dashboard I can only seem to view the current sprint, sprint 1. How do I configure reporting to view all 3 sprints?

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.