How to set "planned for" in Work Item template


Bruno Braga (48013621) | asked Dec 01 '08, 12:02 p.m.
Work Item Template (process / project area inicialization) don't have "planned for" field.

I can configure it in XML?

<workitem>


I would like to create work items and add them in a "default plan" (automatically). But I cant create the Plan using the Project Area Initialization, right?

One answer



permanent link
Johannes Rieken (1.2k1) | answered Dec 02 '08, 3:38 a.m.

I would like to create work items and add them in a "default
plan" (automatically). But I cant create the Plan using the
Project Area Initialization, right?

You are right. Currently it is not possible to create iteration plans on

start up. Please file an enhancement request.

--
Cheers, Johannes