It's all about the answers!

Ask a question

RTC defect management with RQM


Sany Maamari (13243751) | asked Jan 25 '13, 11:16 a.m.
 Hello all, 

We've changed the workflow of the creation of a defect in RTC forcing the person that adds the defects to specify the estimation for the correction of the defects. 

Now, we're using RQM to create the defect, but it doesn't work because in the RQM defect window we cannot add a time estimation, but we specified that the time estimation is mandatory to add a defect. 

Did we do something wrong, is there a way to make it work ? 

Thanks for the help,
Sany

Accepted answer


permanent link
Bob Gallagher (3211) | answered Jan 25 '13, 4:19 p.m.
You need to, through the Work Items section of the Application Administration UI for the Project Area, configure the Inline Work Item Editor or the Lightweight Work Item Creation Dialog for Defect type work items so that the editor UI contains the property you want displayed.
Sany Maamari selected this answer as the correct answer

Comments
Prasad Mandre commented Feb 07 '13, 4:19 a.m.

I am using web client.

I have tried to do it in RQM but fields are not changed. Do I have to make changes in Work Item Editor of RQM or RTC?

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.