It's all about the answers!

Ask a question

MS Project import. Sub task dates not imported.


Paul Tasillo (10665) | asked Jan 16 '13, 10:30 a.m.
JAZZ DEVELOPER
Importing the task list along with their timeliness from MS Project.  I have imported the tasks and sub-tasks already (save the MS Project file as *.xml, import it to a plan); however, the dates of the sub-task were not imported and dates of the tasks were not quite correct.

Are there any work arounds or tricks?

This is CLM 4.0.1.

Be the first one to answer this question!


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.