Planning issue requirements / user stories

Assuming there are a couple of requirements (themes) and user stories to do.
3 sprint teams exist, one can do 500 hours / sprint, the other lets say 300 and 300 .

Now I like to pre-estimate which of my already estimated user stories best fit into the different sprint teams. I like to use any plan in RTC that gives me the calculation automatically based on hours via the 'load' bars.

Question: How do I achieve that without creating a 'pseudo' task below each user story that has exactly the same ammount of estimated hours as the user story ?

Or how do you in your organisation handle that issue ? In my opinion it doesn't matter if you calc in story points or hours, the problem is to fill up the sprint teams.

0 votes


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Dec 10 '12, 10:17 a.m.

Question was seen: 4,036 times

Last updated: Dec 10 '12, 10:17 a.m.

Related questions
Confirmation Cancel Confirm