Vijay Sivashankar (111317) | asked Nov 19 '12, 11:42 a.m.
edited Nov 19 '12, 11:43 a.m.
 I am working on adding widgets to the dashboard to produce reports.

When I add, Execution by Test Schedule, the report shows only one test plan.

Steps:
1) Add Widget
2) Select Execution by Test Schedule
3) Add Widget
4) Click on configure
5) Select 6 test plans
6) Select iteration (The same iterations are listed together when I select other widgets, but for this widget, the iterations are grouped by test plan)
7) Save

Results
The report is showing only one test plan.

Comments
Mark Victory commented Nov 19 '12, 11:50 a.m.
JAZZ DEVELOPER

Hi Vijay,

It seems odd to me that the same milestone "V7FEP6:Milestone 1" is listed multiple times. 
Does that iteration actually apply to all the test plans? 
What happens if you run the report with no Milestones selected.  Do the other Test Plans appear in the report?


Vijay Sivashankar commented Nov 19 '12, 12:08 p.m.
I have tried what you suggested. It created 3 rows, but still doesn't list all rows I expected.

For all widgets I am using, when I go to configure, one iteration per test plan shows up. I am using the shared iterations from the project level. If I have 3 test plans, Milestone 1 (iteration) gets listed 3 times, and if I have 5 test plans -> 5 times and so on. This is a bit annoying, but I thought this is the way the reports are designed.


Here is the new results  


Mark Victory commented Nov 19 '12, 1:06 p.m.
JAZZ DEVELOPER

Hi Vijay,  Do the Test Plans that are not listed have any TCERs related to them?  If there are no TCERs associated to a Test Plan then the Test Plan will not appear in the report.


Vijay Sivashankar commented Nov 19 '12, 4:21 p.m.

Mark, the ones that are not listed have TCERs. I can get those TCER totals listed from other widgets. 


Mark Victory commented Nov 20 '12, 10:02 a.m.
JAZZ DEVELOPER

Hi Vijay,  That is odd.  If you run the Execution By Test Schedule report from the Shared Reports view do you see the same results?

One answer



permanent link
Jun Wang (6077) | answered Nov 21 '12, 11:26 p.m.
Could you please tell us which version of RQM you are using?

Your answer