Lara Ziosi (33811112) | asked Oct 17 '08, 11:48 a.m.
Hi,

While creating an Iteration Plan I have the errors:

Work Item is closed but at least one of its children is open
- This was a Task with no change set attached, Fixed, Verified
Work item is open but all its children are resolved
- This was a Task with a Change set delivered attached to it, the Task was In progress

What should I check to resolve these errors?

Thank you, Lara

One answer



permanent link
Johannes Rieken (1.2k1) | answered Oct 20 '08, 3:34 a.m.
Work Item is closed but at least one of its children is open
- This was a Task with no change set attached, Fixed, Verified
Work item is open but all its children are resolved
- This was a Task with a Change set delivered attached to it, the Task
was In progress

What should I check to resolve these errors?


These warnings are generated based on the parent-child relation ships of
multiple work items. For instance, a high level task might be composed
out of many work items. In case the task is resolved but one of its
children is still open or in progress we generate a warning. If all
children are resolved we warn in case the parent task is not.


--
Cheers, Johannes