Work Item is closed but at least one of its children is open

Hi,

While creating an Iteration Plan I have the errors:

Work Item is closed but at least one of its children is open
- This was a Task with no change set attached, Fixed, Verified
Work item is open but all its children are resolved
- This was a Task with a Change set delivered attached to it, the Task was In progress

What should I check to resolve these errors?

Thank you, Lara

0 votes



One answer

Permanent link
Work Item is closed but at least one of its children is open
- This was a Task with no change set attached, Fixed, Verified
Work item is open but all its children are resolved
- This was a Task with a Change set delivered attached to it, the Task
was In progress

What should I check to resolve these errors?


These warnings are generated based on the parent-child relation ships of
multiple work items. For instance, a high level task might be composed
out of many work items. In case the task is resolved but one of its
children is still open or in progress we generate a warning. If all
children are resolved we warn in case the parent task is not.


--
Cheers, Johannes
Agile Planning Team

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Oct 17 '08, 11:48 a.m.

Question was seen: 6,578 times

Last updated: Oct 17 '08, 11:48 a.m.

Confirmation Cancel Confirm