Including defects in team velocity
Hello all,
I am managing a software development team using SCRUM and RTC version 3.0.1.
We are using Epics, Stories and estimate using story points. I would like to use the Defect artifact for the defects reported. I've realized that defects are by default estimated in hours so I added the story points field to the artifact.
The issue here is that when we solve a defect, if we use the defect artifact, it doesn't add the points to the velocity (despite being the same story point field used in stories).
How can I make the story points from the defect artifacts count in the velocity report?
Thank you so much,
Best Regards,
Goncalo Soares
|
Accepted answer
change the defect to a planning item type in the project process config.. then it looks like Story
(and u have to have tasks for hours spent).. Open Project,-> process config tab, project config->config data ->planning-> work item type categorization, check the box in front of defect. defect is now a workitem used in Planning operations.. >and has story points, but not time spent. but this didn't change as I expected it to. this is on 4.0.. is this a bug? Goncalo Soares selected this answer as the correct answer
Comments
Goncalo Soares
commented Oct 24 '12, 5:26 a.m.
Thank you for the answer! It is working great now. The defect still has hours but we chose to solely use Story Points! |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.