Including defects in team velocity

 Hello all,

I am managing a software development team using SCRUM and RTC version 3.0.1. 
We are using Epics, Stories and estimate using story points. I would like to use the Defect artifact for the defects reported. I've realized that defects are by default estimated in hours so I added the story points field to the artifact.
The issue here is that when we solve a defect, if we use the defect artifact, it doesn't add the points to the velocity (despite being the same story point field used in stories). 
How can I make the story points from the defect artifacts count in the velocity report?

Thank you so much,
Best Regards,
Goncalo Soares

2

1 vote


Accepted answer

Permanent link
change the defect to a planning item type in the project process config.. then it looks like Story
(and u have to have tasks for hours spent)..

Open Project,-> process config tab, project config->config data ->planning-> work item type categorization, check the box in front of defect.

defect is now a workitem used in Planning operations..

>and has story points, but not time spent.
but this didn't change as I expected it to.  this is on 4.0.. is this a bug?
Goncalo Soares selected this answer as the correct answer

1 vote

Comments

Thank you for the answer! It is working great now. The defect still has hours but we chose to solely use Story Points!

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Oct 23 '12, 4:32 a.m.

Question was seen: 4,493 times

Last updated: Oct 24 '12, 5:26 a.m.

Confirmation Cancel Confirm