How to check the actual time taken for 1 round of testing?
How to check the actual time taken to execute 1 round of testing?
We can see the actual time in test case result. When we open a test case result, we can see start time, end time and total run time. I want to see this total run time for 1 round of testing. Like for 1 whole test suite execution record or test case execution record.
And I want to see this total run time, per test case or per tester.
Is there any way to achieve this?
We can see the actual time in test case result. When we open a test case result, we can see start time, end time and total run time. I want to see this total run time for 1 round of testing. Like for 1 whole test suite execution record or test case execution record.
And I want to see this total run time, per test case or per tester.
Is there any way to achieve this?
Accepted answer
How to check the actual time taken to execute 1 round of testing?
We can see the actual time in test case result. When we open a test case result, we can see start time, end time and total run time. I want to see this total run time for 1 round of testing. Like for 1 whole test suite execution record or test case execution record.
And I want to see this total run time, per test case or per tester.
Is there any way to achieve this?
There is currently no automated way to do this. If you have a custom reporting solution (RDDI or Insight) rot could create a report there.