Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Available total hours in work load bar.

Scenario:
The Iteration dates are 18th May 2012 to 15th June 2012.
One user is allocated to the project with no date restriction for 25%.
The user work for 8 hours and ends his day @ 5:00 PM
The current time is 18th May 2012 3:30PM when I load the plan it says 38.5 hours available. Not able to understand how this was calculated.

There are 19 days left in the Iteration if we exclude the last day and week ends.
Which means 19 * (8 * 0.25) = 38 hours.

If we include last day as well then there will 20 days left in the Iteration
Which means 20 * (8 * 0.25) = 40 hours.
As of now (18th May 3:30 PM) 6.5 hours for the day is done which means
40 - 6.5 = 33.5 hours.

It should have been 33.5 hours or 38 hours.
How come it is 38.5 hours?

0 votes


Accepted answer

Permanent link
Hi Aditya,
Where do we mention this 25% allocation done for a project? which template are you using?

Currently i am facing a problem in my scrum template - where all the plan-items show accumulated time till the plan end date - irrespective of the due-date and estimate provided. Even the closed tasks - accumulation time is shown as till plan end-date.

Is this a scheduler problem? Please let me know if you would like to see the process config source

Thanks.
Aradhya K selected this answer as the correct answer

1 vote


2 other answers

Permanent link
The plan will consider it as 20 days as we need to include the last day as well. By default the iteration dates also have time part, this needs to adjusted based on the project.
The dates will be stored in Server locale and 12:00 PM means noon and 12:00 AM means start of the day.
If the last day also needs to be considered then something like 5:00 PM needs to be specified.
So it will 20 * (8/4) = 40 hours.
For 18th May there are 6.5 hours spent for the day. For this plan it will be 6.5/4 = 1.625 hours spent and not 6.5 hours spent. We need to apply the allocation percentages on the today as well.
We always round off to quater of an hours so it will 1.5 hours spent for the date.
That mains available hours in 40 - 1.5 = 38.5 hours.
That is how the available hours is calculated as 38.5 hours.

0 votes


Permanent link
For a Scrum project the expectation is to specify the allocation percentage by each resource on his profile page.
This feature is Web UI only.
Try updating the percentage and check the Gantt, it will surely help in showing the better gantt.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: May 21 '12, 1:30 a.m.

Question was seen: 4,679 times

Last updated: Jun 05 '12, 5:51 a.m.

Confirmation Cancel Confirm