It's all about the answers!

Ask a question

0 h in Estimate field (During Mandatory Conditions)


Sunita Dinakar (11413842) | asked Jan 11 '12, 9:23 a.m.
The value 0 h is a valid entry for estimation field even if the field is mandatory. The question is - Is 0 an acceptable value for the estimate field? I

Cheers,
Sunita

Accepted answer


permanent link
Geoffrey Clemm (30.1k33035) | answered Jan 11 '12, 12:53 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
There are a few edge cases where a 0 cost task is useful.
For example, suppose you have a particular date where a whole set of
tasks need to be done by, but you might need to move that date. One way
to implement that would be to have a 0 cost task set for that date, and
make all the other tasks predecessors of that task. When the date
changes, just update the due date on that task.

Cheers,
Geoff

On 1/11/2012 11:53 AM, sdinakar wrote:
Hi Geoff,

Thank you for the reply. Could you please explain how 0 would be
considered as a valid entry? Any task (work item) should be estimated
against time.

Cheers,
Sunita

gmclemmwrote:
Yes, 0 is a valid value in the estimation field.

Cheers,
Geoff

On 1/11/2012 9:38 AM, sdinakar wrote:
The value 0 h is a valid entry for estimation field even if
the
field is mandatory. The question is - Is 0 an acceptable value for
the estimate field? I

Cheers,
Sunita

Sunita Dinakar selected this answer as the correct answer

2 other answers



permanent link
Geoffrey Clemm (30.1k33035) | answered Jan 11 '12, 10:08 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Yes, 0 is a valid value in the estimation field.

Cheers,
Geoff

On 1/11/2012 9:38 AM, sdinakar wrote:
The value 0 h is a valid entry for estimation field even if the
field is mandatory. The question is - Is 0 an acceptable value for
the estimate field? I

Cheers,
Sunita

permanent link
Sunita Dinakar (11413842) | answered Jan 11 '12, 11:48 a.m.
Hi Geoff,

Thank you for the reply. Could you please explain how 0 would be considered as a valid entry? Any task (work item) should be estimated against time.

Cheers,
Sunita

Yes, 0 is a valid value in the estimation field.

Cheers,
Geoff

On 1/11/2012 9:38 AM, sdinakar wrote:
The value 0 h is a valid entry for estimation field even if the
field is mandatory. The question is - Is 0 an acceptable value for
the estimate field? I

Cheers,
Sunita

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.