It's all about the answers!

Ask a question

Estimate and Progress in milliseconds


Mathias Hermansson (43166) | asked Dec 14 '11, 6:29 a.m.
Hi,

We changed the Scrum process template to be measured in hours instead of story points as the complexity value type. As a result a Story in a plan shows milliseconds instead of days or hours for the Estimate and Progress (only the estimation part, progress shows in hours) columns.

The error only exists in the Web UI, the Eclipse client shows the correct values.

Is there some other setting somewhere to solve this problem?

Regards,
/Mathias

Be the first one to answer this question!


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.