Dear Friends,

i create the RTC project area by using IBM Focal Point. it is already done well. but the problem is, focal point create the additional iteration in project area. i don't want focal point create the additional iteration, i only need the focal Point create the project area only and the iteration will be created based on the process template that i choose when i create the project area in Focal point.

this is the case that i face:
1. i use formal project management process template so it will create the iteration : Release 1.0 and the it's children iteration are req, design, implementation, and testing.

2. but when i already create the project area by using focal point and i check it in RTC, Focal point automatically add the iteration too that is in the same level with Release 1.0.

so the structure will be like this one:
Release 1.0
-) Requirement
-) Design
-)Implementation
-)Testing
Backlog
New iteration from Focal Point <-this is what i mean

please help to do this one?

thanks

0 votes



3 answers

Permanent link
Since this is Focal Point behavior, rather than RTC behavior, you'll
probably want to post this request in the Focal Point forum:

http://www.ibm.com/developerworks/forums/forum.jspa?forumID=1500

Cheers,
Geoff

On 11/18/2011 2:08 AM, adichristantohasan wrote:
Dear Friends,

i create the RTC project area by using IBM Focal Point. it is already
done well. but the problem is, focal point create the additional
iteration in project area. i don't want focal point create the
additional iteration, i only need the focal Point create the project
area only and the iteration will be created based on the process
template that i choose when i create the project area in Focal
point.

this is the case that i face:
1. i use formal project management process template so it will create
the iteration : Release 1.0 and the it's children iteration are req,
design, implementation, and testing.

2. but when i already create the project area by using focal point
and i check it in RTC, Focal point automatically add the iteration
too that is in the same level with Release 1.0.

so the structure will be like this one:
Release 1.0
-) Requirement
-) Design
-)Implementation
-)Testing
Backlog
New iteration from Focal Point<-this is what i mean

please help to do this one?

thanks

0 votes


Permanent link
Hi Geoff,

ok sorry, i will go to the developer works.

thanks

0 votes


Permanent link
No apologies necessary ... one can't be sure in which forum the folks
doing the Focal Point integration with RTC are more likely to hang out.
The likelihood of someone from the Focal Point forum suggesting you
post the request to the RTC forum is non-zero (:-). To avoid that, you
might want to mention in your Focal Point forum post that you've already
posted the question in the RTC forum (:-).

Cheers,
Geoff

On 11/20/2011 11:53 PM, adichristantohasan wrote:
Hi Geoff,

ok sorry, i will go to the developer works.

thanks

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Nov 18 '11, 1:59 a.m.

Question was seen: 4,211 times

Last updated: Nov 18 '11, 1:59 a.m.

Confirmation Cancel Confirm